Flood Relief Schemes Dail Éireann — 2024-02-08 ============================================================ Patrick O'Donovan (FG), Limerick County I will not read into the record the start of the response because I have done so three times already today. I will skip that and I ask that it be put on the record. The OPW will reach a series of important milestones in climate adaptation in 2024, such as: continuing the construction of three major schemes at Glashaboy in the Deputy’s constituency, Morell River and Whitechurch; commencing construction on up to five other schemes at King’s Island, Morrison’s Island in Cork, Crossmolina, about which there has been a bit of conversation, the Poddle River and the River Wad; and progressing up to three further schemes towards substantial completion at Athlone, Springfield and Templemore. These schemes will provide protection to over 600 properties. Outside of these major schemes, as the Deputy knows, local authorities can apply to the Office of Public Works for minor flood mitigation works and the coastal protection scheme. This provides up to 90% of the funding required and, so far, has protected 7,900 properties. I will outline a county-by-county breakdown of the major flood relief schemes that are currently being progressed. In Cavan, there is a scheme at Cavan town, which is at stage 1. In Clare, there is Kilkee, which is at stage 1; Shannon; and Springfield, which is almost at completion. In Cork, there is Ballinhassig, which is at stage 1; Ballymakeery-Ballyvourney, which is at stage 1; Bantry; the Bride River-Blackpool, about which there has been some conversation in the House; Carrigaline; Glashaboy, which is under construction; the lower Lee, which is an enormous scheme that the Deputy will know; Macroom; Midleton; and Morrison’s Island, which has gone out to tender. In Donegal, there is Ballybofey-Stranorlar; Buncrana; Burnfoot; Castlefinn; Donegal Town; Letterkenny; Lifford; Ramelton; and Raphoe. In Dublin, there is the Dodder; Dublin city; Loughlinstown; Malahide; the Poddle River; Portmarnock; Sandymount, which is at the scoping stage; Skerries; and Whitechurch, which is at stage 4. I will come back to the other counties in my next contribution. Additional information not given on the floor of the House. A county-by-county breakdown of the major flood relief schemes and small flood relief projects that are currently being progressed is provided in the tables, including the current status or stage of each scheme.  The 12 flood relief schemes that have reached substantial completion since 2018 are also listed. Table 1.  Major Flood Relief Schemes by County with Scheme Stage. Table 2. Small Projects by County with Scheme Stage. Table 3. Substantially Complete Schemes since 2018 by County. --- Source: Houses of the Oireachtas. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). The Official Report is revised after first publication; the fetch timestamp below identifies the version quoted. Record URI: https://data.oireachtas.ie/akn/ie/debateRecord/dail/2024-02-08/debate/main Retrieved: 2026-08-14T04:52:38+00:00 Sitting date: 2024-02-08