National Development Plan Dail Éireann — 2025-11-05 ============================================================ Jack Chambers (FF), Dublin West There are extensive actions across every barrier and the plan is to have the majority of the practical actions being delivered in 2026. Every action we take is about shortening and truncating timelines for the development lifecycle of critical infrastructure, which is simply taking too long. That means we need to increase our risk appetite. We have too much process and too many decision-makers and there is risk aversion across our systems. Secondly, within government, there is the question of where we can control processes or procedures, so that we can cut unnecessary levels of process which do not add value but simply add time. We have had a forensic assessment of this in recent months. The response to it around the infrastructure report which we publish involves practical actions which will demonstrate shortening of timelines for critical infrastructure and other infrastructure across our economy. On the point about housing, water and wastewater treatment plants are central to the delivery of new homes and many of Irish Water's capital projects are taking far too long. We have secondments from Irish Water and the task force in my Department. They make a positive contribution to the whole area of reform. --- Source: Houses of the Oireachtas. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). The Official Report is revised after first publication; the fetch timestamp below identifies the version quoted. Record URI: https://data.oireachtas.ie/akn/ie/debateRecord/dail/2025-11-05/debate/main Retrieved: 2026-09-21T01:01:05+00:00 Sitting date: 2025-11-05