Schools Building Projects Dail Éireann — 2026-05-28 ============================================================ Hildegarde Naughton (FG), Galway West As the Deputy said, the design team has been instructed by the Department to ready the tender for the completed contract. It will take four to six weeks to publish the tender, with a view to having the contractor on-site in quarter 4 of this year. Each stage of the process is subject to due diligence by the Department within the context of the overall programme and budgetary parameters. However, it remains the Department's priority to deliver a new school building for Gaelscoil Choláiste Mhuire as quickly as possible. Departmental officials will continue to work closely with the school authorities and will meet with them on a regular basis. As the Deputy said, a number of issues arose on site and the Department actively engaged with the design team and the contractor to discuss matters. Those unforeseen matters led to a delay in the project and, as a result, the Department entered into a conciliation hearing to try to reach agreement on a solution to ensure the earliest possible delivery of the school, while respecting its statutory obligations. --- Source: Houses of the Oireachtas. Licensed under CC BY 4.0 (https://creativecommons.org/licenses/by/4.0/). The Official Report is revised after first publication; the fetch timestamp below identifies the version quoted. Record URI: https://data.oireachtas.ie/akn/ie/debateRecord/dail/2026-05-28/debate/main Retrieved: 2026-09-21T01:01:08+00:00 Sitting date: 2026-05-28