Cuirim fáilte roimh an Aire Stáit. I return to the matter of the full reinstatement of the western rail corridor, specifically the 73.5 km stretch between Claremorris and Collooney. I have been left with no alternative but to raise this as a Commencement matter due to the inconsistent and unclear messaging from the Government.
I will give a little bit of background. As a previous speaker said, rail use in Ireland has changed and we, as a population, make more frequent use of rail and demand more services in the rail infrastructure. While the 1980s and 1990s saw prioritisation of road over rail for passengers and freight, attitudes, times and values have changed. In 2016, for example, The Sligo Champion reported that the Sligo-Dublin line was at risk of closing. Just 1.3 million passengers had used the route in 2015. These figures have steadily climbed, especially following the pandemic, and Irish Rail has seen significant passenger growth year on year. Passenger numbers grew from 17.8 million across the network in 2020 to 50.7 million in 2024. Irish Rail expects those numbers to have grown by 5 million in 2025. Freight rail has experienced a similar renaissance.
Times and contexts have changed since the decision was made to close the Claremorris to Collooney rail line. Rail is again recognised as an effective and efficient method of passenger and freight transit. We recognise the environmental benefits of rail and Iarnród Éireann has declared its goal is to be the backbone of Ireland's sustainable transport network.
All other phases of the western rail corridor have either been opened or approved for opening. To exclude Claremorris to Collooney not only denies the people and enterprises of Sligo a vital link to Mayo, Galway and beyond, but it jeopardises the integrity and logic of the entire corridor. Sligo has to connect to it in order for the corridor to achieve its potential. Without the Sligo connection, we risk condemning the corridor to disuse.
This rail corridor is a 73.5 km strip of land. In 2023, it was valued at €957 million. Its untapped value is the final piece of the jigsaw of reopening the western rail corridor. Comments from a number of Government politicians in recent weeks indicated they would like to see a greenway and that there are plans to install a greenway on the existing rail corridor. Will the Minister of State give a commitment that the existing stretch of rail line will be retained for rail use only, as has been indicated by Irish Rail, and that no other structure, including anything described as a temporary structure, should be permitted on it? The narrative we hear is a temporary greenway will be placed on the track to keep it in public ownership. That does not add up because it is already in public ownership. In this day and age, can we honestly see the waste of taxpayers' money involved in creating a temporary structure that will cost millions and then be ripped up to put in a rail line in the future? It makes no sense and is inconsistent with Government policy regarding the western rail corridor. Please, can we get a straight answer and put to bed the idea of a temporary greenway along the existing track?