I acknowledge this is an issue of concern to the Deputy. I understand the flooding that occurred at Drogheda Courthouse on 13 January 2025 resulted from burst pipes. Following the completion of initial repair works, a walk-through inspection of the facility was carried out during the week commencing 20 January 2025. It was agreed at the time that the facility could reopen to the public on 28 January, noting that certain areas, including courtroom 1, would remain unavailable. Further works to courtroom 1 were completed in April 2025 and it became fully operational on 2 May 2025. That marked the completion of all repair works.
As the Deputy is aware, Drogheda Courthouse is part of a seven-courthouse public private partnership, PPP, bundle, which was delivered under a 25-year concession period. Drogheda Courthouse was the first of the projects to be handed over in June 2017 on a landmark town centre site beside the River Boyne. The total cost of the PPP contract covers the design, construction, financing and, importantly, maintenance and repair of the facility. Those costs are met through a single annual unitary charge, which represents a composite payment for all services provided under the contract. It should be noted that the risk and costs of the repairs fell under the ownership of the PPP company, not the Courts Service. The entity that paid for the repair works was not the State but the PPP company.
The total capital funding allocated for courthouse capital works in 2025 amounted to €9.74 million. The total cost of the PPP contract is quite significant but, as I said, the State did not have to pay for it. I cannot give the Deputy an exact detailed breakdown of the charge because it is commercially sensitive and is protected under the terms of the PPP contract.