I thank Senator Collins for raising this. A lot of my answer is specifically in relation to the development of the Limerick-Foynes line. I will try to get more detail about the possibility of it being turned into a passenger-commuter line. I have a piece on Adare as well and a projected timeline that might help the Senator and the people she represents.
On behalf of the Minister for Transport, I thank the Senator for the opportunity to discuss this.
The Limerick Shannon Metropolitan Area Transport Strategy sets out the framework for the delivery and development of the transport system of the Limerick region. A key principle of the strategy is to identify and protect key strategic routes for the movement of freight traffic and to improve access to Shannon Foynes Port. The reinstatement of the Limerick-to-Foynes railway line, to provide a freight service, supports this principle.
The rail freight network in Ireland is currently an underutilised asset. The development of an expanded rail freight network, additional services and facilities will support enhanced modal choice, supply chain resilience, economic development, regional balance and reduced carbon emissions. The reinstatement of the rail connection to the Port of Foynes will be fundamental to the growth objectives for both intermodal and bulk traffic at the port and will play an important role in improving connectivity along the western seaboard. Reinstating the line will give customers more options and support projected traffic growth resulting from mining, power generation and container transport in the region.
At a European level, Shannon Foynes Port is categorised as a core port under the Trans-European Network for Transport, TEN-T, regulation and the Foynes freight line is part of Ireland's core freight network. The regulation requires the port facilities at Foynes to be connected by high-quality rail and road links by 2030.
Works are well advanced on the reinstatement of the rail line, with the project set for completion in October of this year. Track laying was completed in 2025 and works on signalling and telecommunications are progressing. Works are also progressing on the refurbishment of Foynes station, which will be used for staff accommodation on site. The replacement of 13 level crossings with CCTV-monitored crossings will provide an improvement in safety over the previous gated crossings. The works will also connect the Foynes line to the existing network at Limerick. Once the line is commissioned in October, driver training will commence on the route before the first freight services begin operating in early 2027. The reopening of the line will deliver a reliable, frequent, and sustainable logistics option for many companies that currently or in the future will use the port of Foynes.
Linked to these overall works, construction has started on a temporary passenger station at Adare, which is set to support thousands of spectators travelling to and from the Ryder Cup in September 2027. The temporary station consists of a platform and external concourse. Construction, which is expected to take six months, is being progressed alongside works on the reinstatement of the Limerick-to-Foynes freight line.
While intended for temporary use during the period of the Ryder Cup, providing a sustainable way for thousands of visitors to access the event, the reacquisition of the former station building where the temporary platforms will be located also ensures that this access point to the line is safeguarded for future permanent passenger services on the line. In that regard, I note that the Limerick Shannon Metropolitan Area Transport Strategy indicates that passenger services on the Adare line could be considered in future, should development patterns support the viability of a regular service.
On behalf of the Minister for Transport, I hope this response helps clarify the matter. There certainly are positive elements in the reply in terms of the building of the temporary station at Adare. I assume from the Senator's question that she hopes that this is the permanent passenger link that is put in as opposed to the entire length of the Foynes link and I would take positivities from that response, in that they are securing the potential for it being a permanent passenger line. The sooner that would happen after the temporary station is built, the better.