I thank the Deputy for his question. He is referring to developments in Clonmel. The Deputy has spoken to me before about that. I know it is an issue of concern to him.
The rapid build modular units, including those in Clonmel, were built to accommodate beneficiaries of temporary protection fleeing the war in Ukraine. In total, we have 654 units across 11 locations across the country, accommodating 2,640 people in family units of four with children. The long-term use of these units has always been an important aim of the rapid build project. These homes are durable units with an expected 60-year lifespan and are highly energy efficient. They were all developed in an environmentally friendly way.
The Office of Public Works, OPW, is undertaking a post-project completion report to which my Department has contributed. It is still being drafted and is not yet available. To determine the long-term strategy for the sites post temporary protection, we are starting a process of consulting stakeholders. That started back in March 2025 and is chaired by officials from my Department, including people from the OPW and the Department of housing. In tandem with the consideration of the feasibility of potential future uses, this work involves exploring planning regularisation at each site. There has been no final decision made yet on long-term future use as discussions are ongoing. We will explore all potential options within the local areas. These options include social housing and lower-cost affordable housing, such as cost rental. Obviously, the residents there will not be required to vacate this accommodation until March 2027. To meet the conditions of the scheme, they can apply to the new temporary protection transitional scheme. I do not know if they will come within that, but that is an option for them. To date, full occupancy has been maintained with over 90 units relocated since the sites were first occupied. We have not reached a final decision on what will happen after March.